ReConnect IV
ReConnect IV
Grant Awards
Grant Awards
Communities
Elim – Golovin – Koyuk – Little Diomede – Nome – Shaktoolik – Shishmaref – St. Michael – Stebbins – Teller/Brevig Mission – Wales – White Mountian
Awarded ReConnect IV Grant of ~ $35M to:
Communities
Cold Bay – Cooper Landing – Fort Yukon – Galena – Illiamna – King Cove – Moose Pass – Port Lions – Sand Point – Seward – Unalaska/Dutch Harbor
Awarded ReConnect IV Grant of ~ $35M to:
Next Steps
- 1
Identify Engineering Firm, Environmental Consultant & Archaeologist – In Process
- 2
RUS Project Kick-Off – Complete
- 3
Rural Utilities Service (RUS) Notification that Environmental Review – Start Date TBD
– No work on the projects can occur until the successful completion of the environmental review
– Any findings that environmental review requires significant changes to the project will result in the termination of the project - 4
Rural Utilities Service (RUS) Notification that Environmental Review is Complete
– Within 60 days of environmental review completion, the Company must sign and return the Grant Agreement to RUS – In Process
- 5
Tribal Outreach & Coordination – Finalizing Plan
- 6
Finalize Planning and Engineering
- 7
Initiate Construction
- 8
Project Completion & Turn-up